Second stage of connection to the distribution network – includes fulfillment of the works foreseen by connection technical specification, agreement of the technical project by system operator and successful completion of relevance testing defined by articles 150-165 and operational notification defined by articles 138–145 of requirements indicated into the articles 121–136 of “Network Rules” by small capacity power plant.
II stage of connection of small capacity power plants to the electricity distribution network is started after signing the agreement on connection foreseen by the article 69 prima article 6 of the mentioned rules by the parties and entire payment of the fee for the second stage of the connection.
Cost for the connection point (readiness of the network) is determined for connection of small capacity power plant to the distribution network that is established in accordance with the connecting capacity and is calculated in the following way:
Where – Cost of connection point of power plant (readiness of the network)
- Installed capacity of power plant;
– Cost of the connecting capacity 1 MW of power plant
a) For the plants with installed capacity up to 2 MW - k= 60 000 Gel (Including VAT)
b) For the plants with installed capacity up to from 2 MW to 15 MW - k = 300 000 Gel (including VAT)
For an example:
Person/entity who wants connection (applicant) is obliged to pay the cost fully within 20 (twenty) working days after signing the agreement on connection foreseen by the paragraph one of Article 69 prima article 6 of these rules by the parties that is calculated in the following way:
a) Cost for the second stage of connection at organizing the cells in substation owned by the system operator is the sum of the cost for network readiness calculated in accordance with the paragraph 13 of Article 69 prima article 2 of these rules and cost of the second stage for connection to the electricity distribution network.
b) In case of invasion into the system operators’ owned electricity transmission line, second stage of the connection is the cost for network readiness foreseen only by the paragraph 13 of Article 69 prima article 2 of these rules
Cost of the second stage of connection to the electricity distribution network in case of organizing the cell in system operators’ substation
Voltage stage |
Second stage term of connection provision |
Cost for the second stage of the connection, |
During the connection to the 10 kv indoor distribution device |
During the validity term of the agreement on connection |
60 000 |
During the connection to the 35 outdoor distribution device |
218 000 |
|
During the connection to the 35 indoor distribution device |
300 000 |
|
During the connection to the 110 outdoor distribution device |
560 000 |
Person/entity who wants to be connected (applicant) is obliged to prepare the technical draft in accordance with the connection agreement and technical specification issued by System Operator during the second stage of connection to the distribution network and submit to the System Operator as well as to the Transmission System Operator for further agreement.
Person/entity who wants connection (applicant) after fulfillment of the works determined by agreed technical project and technical specification of the connection is obliged to prove fulfillment of the requirements indicated in articles 121-136 of “Network Rules” to the corresponding System Operator as well as the procedures of compliance testing defined by article 150-165 and operative notification determined by the articles 138-145.
Applicant after completing the activities determined by the second stage addresses to the System Operator in written form and notifies on readiness for connection to the distribution network that should be attached by the following:
JSC “Energo-Pro Georgia” will check the rules of acting of electric facilities of the corresponding person/entity who wants connection within 10 working days upon receipt the written form notification on readiness of the one who wants connection, as well as the technical condition of the connection and compliance with the agreed project (hereinafter the - Inspection of the compliance) and issues document proving the relevance (technical document of connection to the network). After this will connect/switches the electric facilities of the ones who wants connection into the network by what procedure for connection to the distribution network is completed.
At new connection to the existed distribution network, all connecting electric facilities and devices should comply with the requirements of the standards and norm established by the legislation acting in Georgia and “Network Rules” of these rules.