Temporary Connection

Standard Connection

In accordance with the paragraph 3 of Article 24 of “Electricity Distribution Network rules” of Resolution No 19 of Georgian Energy and Water Supply Regulatory National Commission”, System Operator is obliged to determine and make public assessable the standard terms of temporary connection to the distribution network and service cost including 220 v10 kW and 380 v 30 kW capacities to the temporary connections from the existed distribution network in 100 m radius; Herewith, system operator is obliged to define other terms differed from this paragraph on temporary connection with the standard term.

Term for the temporary connection with the standard condition should not exceed 12 months, except the case for applying the temporary connection for construction or repair purpose. In such case term for temporary connection with the standard condition can be increased.

Package

 

Type

 

Cost

 

Fulfillment terms

0-10 kW


0.22kV

 

Simple

 

687

 

7 Working days

 

complicated

 

2673

 

20 working days from receipt of the approval on construction

0-10 kW


0.38kV

 

Simple

 

1159

 

7 Working days

 

Complicated

 

3447

 

 20 working days from receipt of the approval on construction

10-30 kW


0.38kV

 

Simple

 

1285

 

7 Working days

 

Complicated

 

5700

 

20 working days from receipt of the approval on construction



In case of standard connection request, person interested in shall address us with the application on temporary connection to the network that will be attached by the tax task or bill confirming the cost for connection of relevant package. System operator reviews the application of the person interested in connection with the standard term within 12 working days and makes decision on satisfaction of the request with the full technological cycle.

Simple connection means such type of connection when for full technological cycle of temporary connection of the object to the network, strengthening of existed distribution network (increase the existed wire section), construction of new network (installing of additional abutments or/and getting any permission is not needed and is embraced only by the required works in connection point of the customer to the system, and in case of necessity by organizing the corresponding wire of metering knot.

Complex connection means all other such type connections that does not belong to the simple type category.

The bellow listed should necessarily be included into the standard request form ( in opposite case the error will be stated):

1. Cadastral code of the real estate and in case of residential customer – number and address of the customer
2. The relevant point of the standard condition publicly offered by the system operator.Corresponding paragraph of the standard term/condition offered by the system operator in public form
3. Requested voltage and capacity
4. Other required paragraphs that are foreseen by the standard request form

Application shall necessarily be attached by:

1. Document confirming the advance payment offered for the temporary connection service with the standard terms by the system operatori n public form
2. Agreement on supply signed by the person who wants connection
3. Photo material
3.1. Full view of the place of the object to be connected and existed distribution network
3.2. View of that place of distribution network from where you want supply to be carried out

The bellow is desirable to be attached to the application:
1. Condition offered by the System Operator in public form (attaching of the printed out version from web page is possible as well)
2. Other documentation that is needed for providing the temporary connection

Annex download here: Application form for standard temporary connection