Temporary Connection

Irregular temporary connection

In accordance with the paragraph 6 of article 24 of “Electricity Distribution Network Rules” of Resolution No 19 of Georgian Energy and water Supply Regulatory National Commission” : Person who wants temporary connection with standard condition addresses System Operator with the standard form application on “temporary connection request” and pays the cost offered for this service by the system operator in public form in advance. Herewith, existence of standard condition does not deprive the right to the customer request connection with non standard condition upon application based on the corresponding technical specification.
 
Non standard all connections that are not foreseen by the standard connection packages. Non standard is the connection when customer himself asks for non standard connection.

Person who wants temporary connection with non standard condition addresses System Operator with the request of issuing the technical specification of temporary connection. System Operator reviews the application of person who wants temporary connection with non standard condition within 10 working days and issues technical specification of temporary connection that includes the point for connection to the existed distribution network, voltage stage and capacity for connection. In case of fulfillment of the temporary connection works with non standard conditions with mutual agreement, agreement between the System Operator and customer is concluded by what commitment of the parties, work due to implementation and issue of ownership/possession formed as a results of this work are precisely defined.

In case of temporary connection with non standard condition, if connection works embrace strengthening of existed distribution network, System operator is authorized to request from the person who wants the temporary connection reimbursement of the expenses needed for strengthening the network completely.
At temporary connection with non standard condition, if the term required for temporary connection exceeds 3 calendar months, after completion of the works foreseen by the technical specification of temporary connection, customer is authorized to organize metering knot himself or ask System Operator to carry out the service of organizing the metering knot. After completion of the works foreseen by technical specification, addresses System Operator with request to start electricity supply and in case of requesting the organization of metering knot by the System Operator will also pay the cost defined for the corresponding package in line with the Annex No 3 of rules.

In case of the case foreseen by paragraph 15 of this Article , System Operator will organize metering knot and will start supply within the term defined by the Annex No 3 of the rules.

Annex download here : Application form of non standard temporary connection