The conditions for connecting the charging point/station to the distribution network apply only to the connection of charging devices to the distribution network, the use of which is not restricted to a circle of persons and is not intended for personal use only. In addition, connecting the charging station to the network does not mean supplying electricity to the facility or a defined area at the place of its placement. The connected power of the charging station does not participate in the calculation of the connected power of the object or the defined area at the place of its placement, and the use of the charging station (electricity consumption) for other purposes is not allowed. The electric charging station must be equipped with an independent power source and must have an individual smart meter.
The person wishing to be connected must apply to the relevant system operator in physical or electronic form (in written form) with the "application for connection to the distribution network of charging stations for electric autonomous vehicles" approved by the Commission's decision.
The person wishing to be connected is obliged to submit the consent of the charging station (device) placement to the system operator with the application, unless the person wishing to connect (applicant) and the real estate owner are the same person.
Connection fee for charging device at 0,4 kv (380/220v) and 6/10 kv to the distribution network is 50% of the new facility connection fee, according to the offered package.
The fee for increasing the capacity for connection of the charging station/plant connected based on the above mentioned paragraph is 50% of the fee of connecting capacity increase determined by the package corresponding for the standard cases of capacity increase (in accordance with the offered packages)
If the location of the charging station (facility or defined area) is not supplied from another supply point, the case where no more than 20% of the capacity for connection is used to supply electricity to this facility and/or its location (territory) shall not be considered as another purposeful use of the charging station. and/or for the generation of electricity with own means of electricity generation. In this case, the user is responsible for the protection and control of the permissible limit of use of the charging station for other purposes in his internal network. However, the burden of proving the authenticity of this information is imposed on the user.
In the case of granting the consent for the placement of a charging station for a specific period, connection must be canceled immediately after the termination or expiration of this consent, if the purpose of the station is not maintained by the owner or by the new owner. The system operator is obliged to inform the user registered at the charging station in the shortest possible time.
The connection of the charging station to the distribution network must be done separately and an individual metering system must be arranged, regardless of whether the place of connection (facility or defined area) is supplied with electricity.
If the charging station and other objects are connected to one cadastral code, the capacity of the connecting object and the charging station's connecting power must be indicated separately.
If the user intends to use the charging station connection for another purpose, he must inform the system operator in advance.
If the connection of the charging station is not carried out during one year period after completion of the connection works provided for in this article or the charging station is not used for 10 years, the system operator is entitled to cancel this connection, after notifying the user 3 months in advance. The user has the right to request the cancellation of the independent power source of the charging station, and the system operator is obliged to fulfill the request in the shortest possible time, without paying any additional fees or costs.